Another Successful Contract Lift Completed by JWI

 

Some interesting pictures of the deflection in the crane boom and of the tag line floating free during the contract lift on a recent JWI job at a food production plant.

 

 

 

 

 

 

The contract lift was planned by one of our Appointed Persons who was on site with the lift supervisor to make sure everything went smoothly.
After the lift was complete we moved the 51/2 tonne transformer and several switch panels through the building using a tirfor winch for additional traction into their final positions. All was successfully completed in the same day.

To discuss similar projects, please contact JWI.